Stonehenge Alliance written representations, responses and rebuttals inserted

IMPORTANT NOTICE: 6 March 2024 – The Planning Inspectorate moved the A303 Stonehenge project documents to a new Beta website here.  Some URLs have changed.  Hyperlinks below are in the process of being updated.  

Planning context

The Stonehenge road scheme was a Nationally Significant Infrastructure Project (NSIP) that required approval by the Secretary of State for Transport.

NSIPs as defined in the 2008 Planning Act apply to large scale developments such as roads (promoted by National Highways), railways, harbours, power stations, transmission lines, oil pipelines, gas storage and others.  These projects are taken through a separate planning application process to obtain a Development Consent Order (DCO) granted by the relevant Secretary of State, in this case, managed by the Department for Transport.   Here is our explainer about NSIPs and the DCO planning process.

2025
  • July 14 – Decommissioning of trial boreholes by National Highways who sent the following statement: “Following the government decision to withdraw funding of the A303 ]Stonehenge project in summer 2024 […] as part of the Development Consent Order, we’re required to decommission the boreholes originally put in place to carry out a variety of soil and water table tests.  We’ve now completed the surveys to access the work needed and can begin to conclude this element of the close down. Work began on the 14 May and will be completed by winter 2025. During this time, you may see National Highways and members of our supply chain working in the surrounding area.” 
  • May 14 – SSWHS was refused permission to pursue its challenge at the Supreme Court. This was bad news not just for the campaign but for all decision making, where according to the courts a Minister needs nothing more than a passing acquaintance with the facts before approving a development. There are also outstanding concerns as to how World Heritage Sites are treated in the planning system that we were unable to get clarified.
  • January 17 –  Our ally, Transport Action Network (TAN), launched their report ‘Connecting South West England: in place of A303/A358 widening’.  We need to recognise that transport networks, particularly public transport, in the South West is in a poor state requiring urgent action.  This was covered by the BBC.  Read more here
2024
  • November –  Application to the Supreme Court submitted: Planning permission for the proposed new road and tunnel remained in place and could be resurrected at any time should the politicians change their minds (up to 4 August 2028).  Two key issues at stake are too important to be left hanging i.e.
    • (i) the protection of decision-making of World Heritage Sites remains unresolved, and
    • (ii) the question of the extent of detail that ministers should know to inform their decision-making.  Consultation with donors to the legal challenge agreed that the case should be pursued.  The application is likely to take 3 or 4 months.
  • October 16 – The Judgment from the Court of Appeal was handed down this afternoon.  Regrettably the application for permission to apply for judicial review was refused by the High Court.
  • July 30 – The Development Consent Order remains in place unless the Court of Appeal quashes the Transport Secretary’s approval.  Judgment expected in the autumn.
  • July 29 – Chancellor Rachel Reeves announced cancellation of the £2.5bn A303 Stonehenge scheme [2] as a “low value, unaffordable commitment” [3].
  • 29 July 2024 – The Chancellor, Rachel Reeves, cancelled the £2.5bn Stonehenge scheme as a “low value, unaffordable commitment”.  Unless the Court of Appeal quashed the Transport Secretary’s approval the Development Consent Order however, remains in place until 4 August 2028.
  • July 24 – The inaccurate amendment from Kenya to overturn the World Heritage Centre’s draft decision to place Stonehenge and Avebury WHS on the List of World Heritage in Danger passed at the World Heritage Committee, effectively overturning all previous Committee decisions despite the letting of the scheme’s contracts.  More here.
  • July 21 – UNESCO’s World Heritage Committee starts its 10 day meeting in Delhi to consider whether to place Stonehenge WHS on the List of World Heritage in Danger.  The World Heritage Centre’s draft decision recommending the WHS on the List of World Heritage in Danger is here (see page 10).
  • July 17 – Close of Court of Appeal hearing.  Judgment reserved.
  • July 15 – International Petition letter handed in to Secretaries of State for Transport and Culture, Media and Sport.  See article.
  • May 17 – Save Stonehenge World Heritage Site given Leave to Appeal the decision by Mr Justice Holgate 
  • April 2 – A360 south of A303 closed for installation of high voltage and fibre optic cables along the A360 to serve the tunnel ahead of legal processes 
  • February 19 – Judge Holgate dismissed the case.  Appeal lodged with the Court of Appeal in March.
  • February 1 – UK Government to submit State of Conservation report to World Heritage Centre with further information on scheme modifications.  Unusually, this has been published by UK Government (DCMS) as a summary only.  Full report suppressed.
2023 – Secretary of State’s DCO Approval
2022 – Redetermination process
2021 – Legal challenge and Quashing of scheme
  • November 30 – Secretary of State’s Statement of Matters and invitation to the DCO Applicant to make further representations for the purposes of his re-determination of the scheme
  • October 27 – Chancellor’s spending review omits budget for A303 Stonehenge scheme – see media report
  • August 10 – Notice that the Transport Secretary will re-determine the DCO Application
  • July 30 – Scheme quashed: High Court judge rules against the Secretary of State’s decision to proceed with the scheme: judgment by The Hon. Mr Justice Holgate: Summary | Full
2020 – Examining Authority’s report and SoS’s Decision
2019 – Examination of draft DCO
  • 2019 Stonehenge Alliance submissions:

– Deadline 1 Submission (25 April 2019) – Suggestions for sites to include in itinerary for Accompanied Site Inspection on 21 May 2019

– Deadline 1 Submission (18 April 2019) – Highways England: Response to Stonehenge Alliance concerning missing information

– Deadline 2 Submission (3 May 2019) – Introduction to Case

– Deadline 2 Submission (3 May 2019) – Written Representation on Principal Issue 3 Alternatives Dr. Kate Fielden, BA, D.Phil. and George McDonic, MBE, BL, DIPLTP, DPA, FFB

– Deadline 2 Submission (3 May 2019) – Written Representation on Principal Issue 4 Biodiversity, Biological Environment and Ecology Dr. Kate Fielden, BA, D.Phil., with advice of Tracé Williams, MSc., BSc.

– Deadline 2 Submission (3 May 2019) – Written Representation on Principle Issue 7 Flood Risk groundwater protection Dr George Reeves, CGeol, CEnv, PhD, MSc, BSc (Hons), FGS, FIMMM

– Deadline 2 Submission (3 May 2019) – Written Representation on Principal Issue 9 Heritage and the Historic Environment Dr Kate Fielden, BA., D.Phil.

– Deadline 2 Submission (3 May 2019) – Written Representation on Principal Issue 10 Landscape and Visual Aspects of the LVIA Andy Norfolk, MSc, Dip.L.A

– Deadline 2 Submission(3 May 2019) – Written Representation on Principal Issue 11 Noise and Vibration (Tranquillity) Clive Bentley, BSc (Hons), CEnv, CSci., MCIEH, MIEnvSc. MIOA

– Deadline 2 Submission (3 May 2019) – Written Representation on Principal Issue 11 Vibration from tunnel boring Rupert Thornely-Taylor, FIOA

– Deadline 2 Submission (3 May 2019) – Written Representation on Principal Issue 13 Transport Planning and Economics Issues Dr Simon Temple, BSc, MSc, D.Phil.

– Deadline 2 Submission (3 May 2019)- Written Representation on the Cultural Heritage Value Report Alan James, MA, BSc.

– Deadline 2 Submission (3 May 2019) – Written Representation on Concerns about consultation on the Scheme Dr Kate Fielden, BA, D.Phil.

– Deadline 3 Submission (from 22 May to 14 June) – Open Floor Hearings Tom HollandDr Simon Temple & Dr Kate Fielden and Dr Temple, Dr Fielden and Dr George Reeve

– Deadline 3 Submission – Summary of Open Floor Hearing on Climate Change Mike Birkin, Friends of the Earth

– Deadline 4 Submission (21 June) –  Our Summary of Oral Representations made at Specific Hearings and Further comments 

– For later submissions and correspondence with Examiners and Planning Inspectorate by the Alliance, please search ‘Stonehenge Alliance’ on the Planning Inspectorate’s Examination Library site

– 2019 Other mutual objectors:

  • Consortium of Archaeologists and the Blick Mead Project Team
  • Council for British Archaeology (CBA)
  • Wiltshire Archaeological and Natural History Society
  • ICOMOS UK
  • Avebury Society

 Examination process 

2018 Draft DCO application submitted
  • December 14 – Stonehenge Alliance to Jesse Norman, Minister of Transport: concerning limited registration period
  • December 8 – Registration of Interested Parties and submit Relevant Representation begins
  • November 16 – Planning application accepted by Planning Inspectorate.
  • October 19 – Draft DCO Application by Highways England received by the Planning Inspectorate
  • 2018 July 17 – August 14 Supplementary Consultation on minor alterations
  • 2018 June 5 – Westminster debate led by Alex Burghart MP
  • 2018 February 8 to April 23 – Statutory consultation on proposed scheme. Cost increases to £1.6bn.

2017

2015/2016 – Route assessment

  • 2015-2016 – Route assessment and identification

2014

  • 2014 – Scheme included in the Roads Investment Strategy. Budget cost £1.2bn.

2013

  • 2013 – A303 feasibility study announced as part of the Autumn Statement
Please share
Facebooktwitter